FEES AND CHARGES LEVIABLE FOR BUILDING & LAYOUT APPLICATIONS:

A) Development Charges (under Section 27 & 28 of the AP Urban Areas (Development) Act, 1975 – Rates as given in G.O.Ms No. 51, MA, Dated: 5-2-1996.

B) Processing Charges: Building Applications @ Rs. 5/- per sq. mt of proposed built up area; Layout applications and Sub-Division applications @ Rs 2/- per sq. mt of land

C) Stationery & Publication Charges: Rs. 5000/- per application

D) In case of plots/sites in unapproved layouts or not forming part of any layout – 10% proportionate open space charges and layout charges.

E) HUDA Board charges (applicable in Appeal/ NOC Cases)

At the time of application only 10% of Processing Charges are collected. HUDA intimates the rest of the charges and fees after the technical approval.

TIME-LIMIT FOR DISPOSAL OF APPLICATIONS IN HUDA:

1. Building Applications: 30 days

Scrutiny and approval & intimation of balance fees & Charges:20 days

Payment of Fees & Charges & release of Plan to local body: 10 days

Total : 30 days

2. Layout Application: 60 days

Scrutiny and approval & intimation of balance fees & Charges:30 days

Payment of Fees & Charges & release of Plan to local body: 10 days

Completion of layout demarcation, fencing of mortgaged area,

etc 10 days

Release of layout after compliance of mortgage deed, submission of Non Encumbrance Certificate 10 days

Total : 60 Days

Final Layout Release:

Scrutiny of application & approval for Final Layout: 10 days

Handing over of open spaces & roads to local body

& submission of their Report 15 days

Release of Final Layout to local Body & Relinquishment deed:10 days

3. NOC Cases:

(A) Normal permissible cases: 30 days

Scrutiny and approval & intimation of balance fees & Charges:20 days

Payment of Fees & Charges & release of Plan to local body: 10 days

Total : 30 days

B) Under Appeal Clause by HUDA Board: After approval by HUDA Board:

intimation of fees & Charges: 10 days

Payment of Fees & Charges & release of NOC : 10 days

4. Land Use Certificates 2 days in respect of Non-MCH Area

3 days in respect of MCH Area

 

 