S.NO Component of work Agreement Amount in lakhs Name of the contractor Probable Date of Completion Remarks  
I. Category-I lakes Annual Maintenance of 3 Lakes          
1 Annual Maintenance of Sewerage Treatment Plant of Saroor Nagar for 2years. 58.51 M/s Waste Encare (1) Pvt. Ltd. Aug'07 Maintenance of contract will be expired in Aug 2007.  
  Annual Maintenance of Sewerage Treatment Plant of Langar Houze for 2years. 35.75 M/s Nikelshwari Consultants Aug'07 Maintenance of contract will be expired in Aug 2007.  
II. Mir Alam Tank          
1 Sewerage Treatment Plant (10 mld) 1241.85 M/s Batiboi Env. Eng. Dec'05 Work in progress.  
2 Peripheral bund Reach-II 31.6 Sri. Satyanarayana Reddy Nov'05 Work in progress.  
3 Revetment Ch. 600m to 3500 36.91 M/s SVR Constructions Nov'05 Work in progress.  
4 Revetment Ch.3500 to 6900 M 41.31 Sri.MVV Satayanarayana Nov'05 Work in progress.  
5 Formation of Road Cambering and slopes with gravel Ch: 0-600 M. 36.57 Sri.N. Janadhan Rao Nov'05 Work in progress.  
6 Chain Link Fencing Reach - 1. 25.76 M/s Hitech Engineers & Fabricators Nov'05 Work in progress.  
7 Formation of peripheral bund with gravel from STP location to IDGAH. 31.05 M/s Aga Construcitons Jan'06 Work in progress.  
             
III. Durgam Cheruvu, Madhapur          
1 Sewerage Treatment Plant (5 mld) 873 M/s UEM India Ltd. Dec'05 Work in progress.  
IV. Category-II Lakes Rangadhamini Lake, Kukatpally,          
1 Formation of peripheral bund. 45.01 M/s Krishi Constructions Dec'05 Work in progress.  
V Gurunadham Cheruvu, Miyapur          
1 Chain Link Fencing 22.87 M/s Anuradha Wire netting Industries.   Work in progress.  
VI Nerella Cheruvu, Kondapur          
1 Widening and strengthening of main bund. 8.92 Sri. S.Surender Reddy Oct'05 Work in progress.