Lakes Division- II

 

                                                                        PROGRESS OF WOKS

 

 

Sl.No

NAME OF WORK

ESTIMATED COST

NAME OF CONTRACTOR

PERIOD OF COMPLETION

REMARKS

I

PEDDA CHERUVU, NACHARAM.

 

 

 

 

I).

Construction of 10 MLD TTP.

1777.80 lakhs

M/s. Degremont

 

12 months

Work in progress work delayed due to court litigation.

II).

Construction of surplus weir at right flank.

17.00 lakhs

M/s. S.V.R Constructions.

 

4 months

Work in progress.

 

III).

Providing Ornamental MS railing to the main bund.

25.00 lakhs

G. Sathya Narayana Reddy

 

4 months

Work in progress.

IV).

 

 

Providing of RCC sewer lines for diversion of drainage.

88.00 lakhs

S.S Constructions

 

5 months

Work in progress.

 

V).

Providing chain link mesh fencing to peripheral bund.

37.35 lakhs

M/s. Anuradha Wire Netting

 

4 months

Due to court cases work could not be taken up.

 

 

 

 

 

 

 

SAFILGUDA

 

 

 

 

 

   I).

Operational and Maintenance of TTP 0.6 MLD

28.00 lakhs

P.Venkateshwar Rao

24 months

Work in progress

 

 

RAACHERUVU

 

 

 

 

 

 

I).

Strenthening and widening of existing main bund.

49.54 lakhs

N.Babu Rao.

 

4 months

Work in Progress.

 

 

ALWAL CHERUVU

 

 

 

 

 

I).

Formation of peripheral bund with gravel to protect at Alwal Cheruvu.

64.00 lakhs

S.Surender Reddy

 

4 months

Irrigation / Revenue authorities to demarcate Lake boundary on ground work to be started after demarcation.

 

 

PEDDA CHERUVU, MANSOORA ROAD,

 

 

 

 

 

I).

Consturction of surplus weir arrangement in CRS  Masonry and barbed wire fencing

23.50 lakhs

M/s Telangana Waddera Sangam.

 

4 months

Irrigation / Revenue authorities to demarcate Lake boundary on ground work to be started after demarcation.

 

 

NELLA CHERUVU, UPPAL

 

 

 

 

 

I).

Formation of peripheral bund with good gravel and revetment with pointing at Nacharam reach-I.

33.31 lakhs

Sushee Hi-Tech

 

2 months

No work could be taken up due to dispute on ownership of the land.

 

II).

Formation of peripheral bund with good gravel and revetment with pointing at Nacharam reach-II.

40.57 lakhs

Sushee Hi-Tech

 

2 months

Balance work is held due to Land ownership disputes.

 

III).

Formation of peripheral bund with good gravel and revetment with pointing at Nacharam reach-III.

36.60 lakhs

Sushee Hi-Tech

 

2 months

Completed

 

IV).

Construction of 5 MLD TTP at Nalla Cheruvu.

819.63 lakhs

M/s. Ramkee infrastructure

Ltd.                                          12 months                                           

Work held up due to Court stay Orders.

 

KAMUNI KUNTA

 

 

 

I).

Desilting lake bed and formation of peripheral bund with Desilted Earth.

14.00 lakhs

Unitech Earth Movers              

                                                  45 days

Due to court stay work stopped.  Agreement closed.

 

PEDDA CHERUVU NACHARAM

 

 

 

II).

Formation of ring bund along the periphery of the lake by using debris gravel Reach-I.

28.85 lakhs

Sushee Hi-Tech                     

                                                 3months

Due to court stay work stopped.  Agreement closed.

III).

Formation of ring bund along the periphery of the lake by using debris gravel Reach

30.90 lakhs

Sushee Hi-Tech                     

                                                 3months

Due to court stay work stopped.  Agreement closed.

IV).

Formation of ring bund along the periphery of the lake by using debris gravel Reach

22.30 lakhs

Sushee Hi-Tech                     

                                                 3months

Due to court stay work stopped.  Agreement closed.