Lakes Division- II
PROGRESS OF WOKS
|
Sl.No |
NAME OF WORK |
ESTIMATED COST |
NAME OF CONTRACTOR |
PERIOD OF COMPLETION |
REMARKS |
|
I |
PEDDA CHERUVU, NACHARAM. |
|
|
|
|
|
I). |
Construction of 10 MLD TTP. |
1777.80 lakhs |
M/s. Degremont |
12 months |
Work in progress work delayed due to court litigation. |
|
II). |
Construction of surplus weir at right flank. |
17.00 lakhs |
M/s. S.V.R Constructions. |
4 months |
Work in progress. |
|
III). |
Providing Ornamental MS railing to the main bund. |
25.00 lakhs |
G. Sathya Narayana Reddy |
4 months |
Work in progress. |
|
IV). |
Providing of RCC sewer lines for diversion of drainage. |
88.00 lakhs |
S.S Constructions |
5 months |
Work in progress. |
|
V). |
Providing chain link mesh fencing to peripheral bund. |
37.35 lakhs |
M/s. Anuradha Wire Netting |
4 months |
Due to court cases work could not be taken up. |
|
|
SAFILGUDA |
|
|
|
|
|
||||
|
I). |
Operational and Maintenance of TTP 0.6 MLD |
28.00 lakhs |
P.Venkateshwar Rao |
24 months |
Work in progress |
|
||||
|
|
RAACHERUVU |
|
|
|
|
|
||||
|
I). |
Strenthening and widening of existing main bund. |
49.54 lakhs |
N.Babu Rao. |
4 months |
Work in Progress. |
|
||||
|
|
ALWAL CHERUVU |
|
|
|
|
|
||||
|
I). |
Formation of peripheral bund with gravel to protect at Alwal Cheruvu. |
64.00 lakhs |
S.Surender Reddy |
4 months |
Irrigation / Revenue authorities to demarcate Lake boundary on ground work to be started after demarcation. |
|
||||
|
|
PEDDA CHERUVU,
MANSOORA ROAD, |
|
|
|
|
|
||||
|
I). |
Consturction of surplus weir arrangement in CRS Masonry and barbed wire fencing |
23.50 lakhs |
M/s Telangana Waddera Sangam. |
4 months |
Irrigation / Revenue authorities to demarcate Lake boundary on ground work to be started after demarcation. |
|
||||
|
|
NELLA CHERUVU,
UPPAL |
|
|
|
|
|
||||
|
I). |
Formation of peripheral bund with good gravel and revetment with pointing at Nacharam reach-I. |
33.31 lakhs |
Sushee Hi-Tech |
2 months |
No work could be taken up due to dispute on ownership of the land. |
|
||||
|
II). |
Formation of peripheral bund with good gravel and revetment with pointing at Nacharam reach-II. |
40.57 lakhs |
Sushee Hi-Tech |
2 months |
Balance work is held due to Land ownership disputes. |
|
||||
|
III). |
Formation of peripheral bund with good gravel and revetment with pointing at Nacharam reach-III. |
36.60 lakhs |
Sushee Hi-Tech |
2 months |
Completed |
|
||||
|
IV). |
Construction of 5 MLD TTP at Nalla Cheruvu. |
819.63 lakhs |
Ltd. 12 months |
Work held up due to Court stay Orders. |
||||||
|
|
KAMUNI KUNTA |
|
|
|
||||||
|
I). |
Desilting lake bed and formation of peripheral bund with Desilted Earth. |
14.00 lakhs |
Unitech Earth Movers 45 days |
Due to court stay work stopped. Agreement closed. |
||||||
|
|
PEDDA CHERUVU
NACHARAM |
|
|
|
||||||
|
II). |
Formation of ring bund along the periphery of the lake by using debris gravel Reach-I. |
28.85 lakhs |
Sushee Hi-Tech 3months |
Due to court stay work stopped. Agreement closed. |
||||||
|
III). |
Formation of ring bund along the periphery of the lake by using debris gravel Reach |
30.90 lakhs |
Sushee Hi-Tech 3months |
Due to court stay work stopped. Agreement closed. |
||||||
|
IV). |
Formation of ring bund along the periphery of the lake by using debris gravel Reach |
22.30 lakhs |
Sushee Hi-Tech 3months |
Due to court stay work stopped. Agreement closed. |
||||||